Quick reference
Estimator’s formula sheet
Every formula is only as reliable as its scope, unit and source data. State denominators and percentage bases.
Measurement
Unit conversion controls
Write the unit beside every input. If units do not cancel to the BOQ unit, the calculation is incomplete.
| From | To | Method | Example | Common error |
|---|---|---|---|---|
| mm | m | ÷ 1,000 | 75 mm = 0.075 m | Dividing by 100 |
| m² + thickness | m³ | Area × thickness (m) | 250 m² × 0.1 m = 25 m³ | Using thickness in mm |
| m³ | t | × density t/m³ | 5 m³ × 2.4 t/m³ = 12 t | Using kg density without ÷ 1,000 |
| litre | m³ | ÷ 1,000 | 250 L = 0.25 m³ | Confusing litre and kilolitre |
| kg | tonne | ÷ 1,000 | 3,500 kg = 3.5 t | Rate remains per kg |
| Monthly | Hourly | ÷ actual paid/productive hours | Use roster/calendar | Assuming 160 hours universally |
| Pack | Installed unit | Ceiling(net ÷ coverage) × pack cost ÷ net | Small orders affected by pack rounding | Buying fractional packs |
| Loose volume | Pay volume | Use stated state conversion | 1.22 loose/bank factor | Applying factor in wrong direction |
Final controls
Tender review checklists
Ticking a box is not evidence. The reviewer must locate the supporting document or calculation.
Error prevention
Twenty mistakes that destroy tender prices
These errors recur across goods, services and works tenders.
| No. | Error | Consequence | Control |
|---|---|---|---|
| 1 | Pricing only the BOQ description | Contract and specification obligations omitted | Cross-reference requirement map |
| 2 | Supplier quote treated as final rate | Delivery, installation and warranty omitted | Normalise complete delivered scope |
| 3 | Wage used as labour cost | Employment burden and relief lost | Build burdened productive rate |
| 4 | Paid hours treated as productive | Labour unit rate understated | Use observed achievable output |
| 5 | Theoretical plant output used alone | Fleet and downtime understated | Cycle and bottleneck analysis |
| 6 | Blanket waste percentage | Loss over- or understated | Layout, yield and pack calculation |
| 7 | Preliminaries copied as a % | Duration and site duties missed | Fixed/time/value schedule |
| 8 | Overhead confused with profit | Business cost not recovered | Separate cost and return layers |
| 9 | Markup called margin | Profit lower than intended | Use algebra and final margin check |
| 10 | Risk included several times | Uncompetitive price | Risk register and duplication review |
| 11 | Known scope put in contingency | Unclear and uncontrolled estimate | Move known cost to base |
| 12 | VAT duplicated or misrepresented | Wrong total / compliance issue | Verify status and quote basis |
| 13 | Old quote used without adjustment | Price validity exposure | Date, validity and escalation control |
| 14 | Optimistic framework quantity | Fixed cost unrecovered | Volume sensitivity / separate setup |
| 15 | No cash-flow forecast | Profitable tender cannot be funded | Monthly cash and facility review |
| 16 | m, m² and m³ mixed | Major conversion error | Unit scan and dimensional check |
| 17 | Addendum not flowed into estimate | Wrong scope or non-responsive bid | Addendum register and version lock |
| 18 | Client budget forced into BOQ | Hidden loss and arbitrary rates | Independent build-up, then target review |
| 19 | Late uncontrolled edit | Forms and totals disagree | Price freeze and one final owner |
| 20 | No award handover | Delivery team misses assumptions | Estimate-to-contract handover pack |
Language
Tender and estimating glossary
Search the terms used throughout the course. The live tender or contract may define a term differently.
Primary references
Official South African sources
Use these primary sources to verify current procurement, forms, contractor and tax information.
eTender Publication PortalCurrent public-sector tender opportunities and procurement
data
↗
Central Supplier DatabaseSupplier registration and information maintenance
↗
National Treasury standard bidding formsCurrent SBD forms published by OCPO
↗
Preferential Procurement Regulations, 2022Official Gazette PDF; check transitional
applicability
↗
PPR 2022 implementation guideNational Treasury implementation guidance
↗
Public Procurement Act 28 of 2024Enacted Act; verify commencement and transitional
position
↗
Draft General Public Procurement Regulations 2026Draft consultation material—not final
law
↗
CIDB Standard for UniformityEngineering and construction works procurement standard
↗
CIDB Register of ContractorsGrading overview and current tender value information
↗
SARS VAT registrationCurrent compulsory and voluntary registration information
↗
SARS VAT overviewCurrent standard rate and vendor information
↗
National Treasury General Conditions of ContractGeneral conditions used with applicable
public procurement documents
↗
Continue training